919 Third Avenue

 

This building was erected in 1971. In 1996 Roof Solutions investigated the roof and found it had already been replaced at least one time. The roof was a conventional design and completely water soaked. It too needed to be replaced.

A new roof would be the third roof in this buildings relatively short 25 year history. A roof design that would not be significantly affected by the poor details and abuse was developed. Over several years the roof design was installed successfully.

In 2004 the concrete runway was evaluated and restored. The runway’s substrate was wet, the concrete was deteriorated and reinforcing rebar placed less than an inch below the concrete’s surface.

A successful restoration was accomplished without replacement saving tens of thousands of dollars and                                                             reduced disruption.